Epsom system installed in October 2010

Technical Specification

This 3.12kWP system was installed in October 2010 on two south and one west facing pitch and involved the removal of a chimney to eliminate shading losses.


epsom-solar-panels








sanyo-solar-panels-performance-surrey







Following the first two years of operation the system has performed well with energy generation exceeding the SAP projection by approximately 18%. Over 5500 units of electricity had been generated in 2 years earning over £2500, a sum which met over 80% of the properties electricity and gas bills in the corresponding period. 









Installed by 1st Solar PV Ltd